Date constraint

S
Sunil Babu 👤 Member for 15 years 6 months

 Hi friends,

What will happen if the activity with start date constraint not started even after the constraint date,

any thing wrong if we schedule with that constraint..?

Your views are most welcome.

regards

Sunil

M
Mike Testro 👤 Member for 20 years 5 months

Hi Sunil

It depends on your software and the type of start constraint.

Please be a bit more specific.

Best regards

Mike Testro