Dear All Planners,
Why P6 dosent consider the highest TF in the schedule as the project TF? Seee the example below why P6 not consider teh -67 as the highest TF?
Total -45
WBS1 -45
WBS2 -67
Thank you for any help,
Regars,
HANSON
Dear All Planners,
Why P6 dosent consider the highest TF in the schedule as the project TF? Seee the example below why P6 not consider teh -67 as the highest TF?
Total -45
WBS1 -45
WBS2 -67
Thank you for any help,
Regars,
HANSON
Got it.. Thanks a lot Ron..
Hanson
Are you really looking at a TF or negative 45 and negative 67 and if that is true then -45 is higher than -67 (closer to zero) Surely you don't have a -67 day total float in your schedule as that is indicating that you would over run your completion date that is showing in the schedule currently by 67 days
Ron