varience BL-finish

S
Sunil Babu 👤 Member for 15 years 6 months

Helo Friends,

When I scheduled a project I found an activity with finish  date jun15 and  as of may 1st datadate it is showing -212 d varience in BL-finish , actual % complete of that activity is 95% why that activity showing -212days of delay..?My question is

any mistake in selecting VARIENCE BL-FINISH in delay analysis ...is it correct? 

Regards

Sunil.

R
Raymund de Laza 👤 Member for 16 years 6 months

Hi,

The discripancies maybe due to the wrong Planned Dates and/or the assigned Baseline.

 

As an advice..... When intends to Make a New Program as Baseline, do note of the following..

1. Make sure the Project Planned Start = Data Date
2. Make sure that all Activities Planned Start = Early Start = Start
3. Make sure that all Acitivites Planned Finish = Early Finish = Finish

Then the same program shall be used as the current program for monitoring.

D
Daniel Limson 👤 Member for 24 years 7 months

Sunil,

check the details and see what is pushing that variance to -212d delay, it may just be accidental error in your update.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts