Helo Friends,
When I scheduled a project I found an activity with finish date jun15 and as of may 1st datadate it is showing -212 d varience in BL-finish , actual % complete of that activity is 95% why that activity showing -212days of delay..?My question is
any mistake in selecting VARIENCE BL-FINISH in delay analysis ...is it correct?
Regards
Sunil.
Hi Daniel,
Thanks for reply.
Sunil
Hi Raymund,
Thanks for your reply.
Regards
Sunil
Hi,
The discripancies maybe due to the wrong Planned Dates and/or the assigned Baseline.
As an advice..... When intends to Make a New Program as Baseline, do note of the following..
1. Make sure the Project Planned Start = Data Date
2. Make sure that all Activities Planned Start = Early Start = Start
3. Make sure that all Acitivites Planned Finish = Early Finish = Finish
Then the same program shall be used as the current program for monitoring.
Sunil,
check the details and see what is pushing that variance to -212d delay, it may just be accidental error in your update.