closing out schedule

S
Sunil Babu 👤 Member for 15 years 7 months

Hi friends,

what should be thre primary concerns when we are making a 

closing out schedule for an industrial project.Your views are most welcome.

Regards

Sunil

D
Daniel Limson 👤 Member for 24 years 8 months

Sunil,

Do a check list of all outstanding works and/or tasks and then do a programme and agree it with the Engineer. Be sure that the Engineer signs-off for every item completed in your checklist. Normally, the check list will involve outstanding works or punchlist items or any outstanding documentation like As-Built Drawings, O&M manuals, Warrantees, Training, etc.

Hope this helps.

Regards,

Daniel

 