Hi All,
I want the actual units of a certain (Labor) Type resource and not the actual units of the combination of resources allocated to the activities to update the UNITS % COMPLETE . e.g., for a given task, i have two types of resources allocated to it, one of type LABOR and the other of the type NONLABOR..my question : can the UNITS % COMPLETE be only updated based on the quantities of the LABOR type only resource?
Thanks a bunch
Moe
P6 considers only labour & non labour units for deriving units % complete and will not consider material units for calculating percentage complete.
The calculation of Activity % Complete = Units % Complete = (Actual Labor Units + Actual Nonlabor Units) ¸ (Actual Labor Units + Actual Nonlabor Units +Remaining Labor Units + Remaining Nonlabor Units).
If multiple resources have been assigned to the activity it would be sum of all labor and nonlabor units.