Hi,
I updated a plan with costs and new dates.
I then opened another plan and updated Costs and dates using the same layout.
I then went back into the first plan and noticed that some costs and dates had changed.
Does anybody know why this has happened?
Thanks
Richard.
It may be a case that you opened the both the programs in the same layout. becuase the layouts are customized according to current program and ofcourse the data date is also the part of the customized layout for a program.
i hope you have got the point.
regards