Hai Every one,
I findind a problem to get the overall % complete to the project.
i am updating the % progress for each activity in primavera, but i am unable to get the cumulative % progress at each WBS and for project also.
When i am updating the same in MS Project, it is showing the overall % complete.
Can anyone help in this regard,
Thanks in advance.
Mr. Geholt,
Thank you very much fo your reply.
My project is not cost loaded and i am updating on duration based.
In that case how to get the rolled progress acheived.
Thanks in advance.
Chandu.
Mr. Geholt,
Thank you very much fo your reply.
My project is not cost loaded and i am updating on duration based.
In that case how to get the rolled progress acheived.
Thanks in advance.
Chandu.
Physical % complete will not roll up to WBS level u have to use Performance % comp. but ur schedule should be cost loaded ..