My schedule is about 9000 lines with about 500 resources, Is there a way of auto-levelling the resources and not affect the finish date of the project?
Resource Levelling
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
If resources are sufficient the finish will not move.
The purpose of resource leveling is creating realistic plan. Applying resource leveling you may find what resources are needed to be able to finish on specified date.