Create Baseline & Update Schedule in P6 v7

Can anyone tell me the simple procedure on how to create baseline and once the baseline is saved then how to update the schedule.

Thanks.

M
Mushtaque Ali 👤 Member for 18 years 9 months

MAINTAIN BASE LINE :

First i am going to brief  you the Baseline can be create 

  • Current project as a Baseline
  • convert another project to new Base line       

Step 1.  Go to Project and select from the drop down maintain baseline and press add button then new window will be appear there you can select either you want to add 1. Current Project as Base line or Convert another Project as New Baseline Choise is yours

[[wysiwyg_imageupload:2119:]]

 

[[wysiwyg_imageupload:2120:]]

 

Step 2. Go to Project and select from the drop down Assign Baseline.

Step 3. Go to View and and select from the drop down Bars and tick the Primary Base line under disply. You should now see the Project baseline bar is displayed, generally bar colour is in yellow you can change as per your wish.

[[wysiwyg_imageupload:2121:]]

J
Johannes Vandenberg 👤 Member for 16 years 4 months

 

Hi Sahibzada

Is this what you are looking for ?

Try this; In P6 you have 3 steps to ensure that the baseline milestones are not shifting during updating the schedule.

Step 1: Go to maintain baseline and add new baseline. Give the baseline and clear identification. Say BASELINE APRIL 2012

Also make the BASELINE APRIL 2012 your PROJECT BASELINE. this is at the lower part of the same form

Step 2: Go to Assign baseline and assign the baseline BASELINE APRIL 2012. 

Step 3: Go to View bars and select the tick box for PROJECT BASELINE. 

You should now see that the PROJECT BASELINE bar is displayed , usually in a yellow color, under the green colored bars.

If you now update the schedule the yellow PROJECT BASELINE bars and milestones are remaining in the same position and the remaining duration bars these are color green are moving.

In short, maintain the baseline, assign the baseline and display the baseline

Johannes

S
Sahibzada Moqeem 👤 Member for 15 years 1 month

 

Can anyone tell me the simple procedure on how to create baseline and once the baseline is saved then how to update the schedule.

Thanks!

At your Early response!

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts