Updating Problems

Dear all,

I am finding a problem that i had set a baseline for a project work programme. now when i am updating it with new data date the baseline milestones are also shifting. i want the baseline milestones to be shown as separate not shifted. can anyone help me out please ?

K
Krishna Sivachand Kodali 👤 Member for 14 years 9 months

Hai

I have also faced the same problem and now i got it.

First you have to maintain the baseline of a particular project and then assign the same afterwards.

I think you are doing in reverse thats why you are facing the problem.

J
Johannes Vandenberg 👤 Member for 16 years 5 months

Hi Muhammad

Can be several issues.

Try this; In P6 you have 3 steps to ensure that the baseline milestones are not shifting during updating the schedule.

Step 1: Go to maintain baseline and add new baseline. Give the baseline and clear identification. Say BASELINE APRIL 2012

Also make the BASELINE APRIL 2012 your PROJECT BASELINE. this is at the lower part of the same form

Step 2: Go to Assign baseline and assign the baseline BASELINE APRIL 2012. 

Step 3: Go to View bars and select the tick box for PROJECT BASELINE. 

You should now see that the PROJECT BASELINE bar is displayed , usually in a yellow color, under the green colored bars.

If you now update the schedule the yellow PROJECT BASELINE bars and milestones are remaining in the same position and the remaining duration bars these are color green are moving.

In short, maintain the baseline, assign the baseline and display the baseline

Johannes

Forum Sponsor

Top Posters

Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts
Tony Wright
4 posts
Arshman
0 posts
Stan Remiszewski
1 posts
GeoVe
0 posts
JAGAN REDDY MUSUKU
0 posts
Nick Johnson-Pond
3 posts