Retained Logic & Progress Override

Hi all planners,

I was studying Retained Logic and Progress Override options in P6. And understood well about Retained Logic also I understood that the result under Progress Override are not realistic. Then, the question raised that if the results are not realistic then why this option is there in the P6?, also what is the difference between “Retained Logic” and “Actual Dates” I am sure there lot of experienced planners who can satisfy me.

Cheers

T
Tanveer Ahmad Niazi 👤 Member for 20 years 6 months

Thanx Mr. Ronald Winterfor your reference, I studied the threads and the articles referred. It’s  now  pretty much clear to me that where and when should I use the option of “Progress Override” but I think I need some practice to get the complete sense of it. Thanx again

R
Ronald Winter 👤 Member for 23 years 5 months

Tanveer,

 If you will look to the right of your screen at the top, you will see a section titled, “More Like This”.  Click on any of the suggested links to answer your questions.  Good luck!

Forum Sponsor

Top Posters

Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts