Hi All
Please could someone help me .
I have set the calender to be 24h ,However if i have a duration of 1 day on the schedule it shows as finishing the following day . E.G if Activity A Duration =1 day , starts 1st April ,the finish date is shown as 2nd April.I understand that if i use the hour as the unit of measurement then i have to physicall y cahnge the finish time to 11.59.then it give me the result ,.is ther a way i can set the calender so that i do not have to do this physically always .Thanks in advance for your Help
Martin,
While you can have P6 DISPLAY only days, it always works in hours (and minutes). Even though it is not pleasant to do so, you must display hours if you intend to have accurate schedules. Good luck!
Hi,
When you enter 1 day as the activity duration this looks at the calendar and then multiplies it by the number of hours in the working day, therefore the hours entered on your task will be 24.
Check the time you are scheduling the data date to, this will need to be 00:00
Check the predecessor has the same calendar, as if it different it could effect the start of your 24hr activity.
HTH