Linkining between Tasks in two different files

A
Ahmed KHR 👤 Member for 15 years 7 months

Planners,

I have détail plannings for the structures, This structures is including on the master schedule as macro activities (Major works, Finitions).

 

Link between this detail schedules and the Master scedule on MSP2007?

Regards.

A
Alexandre Faulx-Briole 👤 Member for 23 years 5 months

Hello Ahmed and Jhorbam,

a much easier way of doing:

open all the MSP schedules you want to link tasks between,

click Window, New, and select all the necessary files; MSP will build a new project with all the selected individual projects included

link the tasks by using the mouse; do not enter the predecessor number in the Predecessor column, as MSP would link the tasks in the same project

Alexandre

A
Ahmed KHR 👤 Member for 15 years 7 months

Thanks a lot Jhobram, yes its verry simple after your explication.

J
Jhorbam Baena Orozco 👤 Member for 16 years 9 months

Hi, is very easy...is like create a local link...i sugest you before all place all the files in the same directory.  After that, open the file where you wanna start to create the external links and select the activity to create the link (to here, all is normal ok), when you have the window open only in the ID field write the full path, and the file, and the id of activity that you wanna link...by example:

Path =

File 1= Plan1

File 2= Plan2

Ok, i wanna link the activity 25 of the File2 into the 4 activity of the File1...ok then, i have to open the File1 and select the Activity 4 and double click to open the task information window and selecte predecessor tab...in the field ID i write this:

c:\planner\File2.mpp\25

And this is all!!!!

 

Forum Sponsor

Top Posters

James Williams
74 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts
Neil Atkinson
5 posts
Trian Asmoro
1 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts