Milestones and Key dates WBS

 

Hi Knowledgeable professionals,

Please should all milestones be gathered under a unique WBS (e.g. a WBS named "Milestones and Keydates") or should it be inserted within the WBS containing the deliverable that is related to the milestones (e.g. Engineering milestones should be under "Engineering WBS", MEP milestones under "MEP works" WBS).

Thanks in advance for your valuable help.

Abdulhafiz.

A
Abdulhafiz Suara 👤 Member for 14 years 11 months

Thanks again Raymund, a friend here also suggested the same solution. However, I think I finally got around to group by Activity code as well as WBS. I appreciate your inputs man!

Cheers,

Abdulhafiz

A
Abdulhafiz Suara 👤 Member for 14 years 11 months

Thanks Raymund, I follow your reasoning but the challenge Im having with Activity codes is that is will just group the schedule into "Milestones" and "No Milestones" categories which is not so cool for presentation purposes. Or is there a way to group by Activity codes as well as WBS especially in P6? Thanks again for inputs.

 

Regards,

Abdulhafiz

R
Raymund de Laza 👤 Member for 16 years 7 months

AbdulHafiz,

I suggest you insert those key dates within the same WBS with the related tasks and create acitivty codes to group milestone/key dates altogether for reporting purposes organized by activty codes accordingly.

Forum Sponsor

Top Posters

Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts