Integrate P6 with Esimate

R
Rob Kane 👤 Member for 22 years 4 months

Hi Guys,

Has anyone out there had any experience with integrating the schedule with the estimate.

My organisation currently works with an estimating depatment that goes off and builds an estimate (they use expert & or Candy) at the same time we have the planners building a project schedule in P6.

We dont currently have a system to integrate the two sources of data. So I have the crazy situation where I have an estimate with 40 000 lline items, right down to litres of fuel and a project schedule that has around 1000 activities.

There is notihng that ties them together.

Does anyone have any info on the correct process /  procedure to get this working that they are willing to share?

Thanks

Rob

 

 

 

S
Sankar Vijayan 👤 Member for 15 years 8 months

Hi

The best software for integration is CCS Candy .I  am a costing Engineer & i am now using Excel for preparing various MIS reports .I think if u use candy & give good inputs its a fantastic software

 

Regards

Sankar

R
Rob Kane 👤 Member for 22 years 4 months

Thanks for the reply Mike, I think we are following similar thought processes. This is what we have had to do to get the alignment with Estimate & Schedule - we have had to go back to it and allocate a scope ID / WBS to each line and then summarize up to Plant Labour Material etc.

 

I suppose the obvious answer to my question is the steps need to be followed properly 1. Identify Scope 2. Define WBS 3. Build estimate & Build Schedule (and get these built together not independently).

M
Mike Testro 👤 Member for 20 years 5 months

Hi Rob

This is where your WBS numbers are most effective.

I assume that your estimate breakdown is on some sort of Spreadsheet.

You need to go through it and allocate your programme WBS codes to the estimate lines.

Then summarise the cost elements to each WBS entry to transfer to the programme resource section.

This is very cumbersome in Excell but works very simply in Lotus 123.

In some organisations they have standard WBS codes that both the estimators and planners use - maybe you should discuss this with your managers.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts