Actually I am doing that by using UDF and Global Chang taking into consideration that the finish progress bar shuold be based on the the schedule %.But I was looking for an easier way.
Baseline Progress Bar is not available in P6 in my opinion.
However if you want to show using the UDF, create UDF say Min (From or Start Date) and Ali (To or Finish Date).
On the bar option, create a Bar Name - BL Progress, Timescale - User Dates, then select the UDF for User Start Date and Use Finish Date. On the Bar Style - make the style & row the same as your baseline Bar.
I could not see the attached picture ,however I'd like to show the blue bar on the baseline bar as we used to get it from P3,on other words, to show the planned progress on the baseline bar.
I am aware that it can be done by the user define fields,but it is lettle bit complicated,like to get an easy way.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hi Ayman
I have inserted a link to my website. Is this what you like to see?
If so, and need more information let me know.
http://plannenvoornietplanners.net/opgeven-van-de-voortgang/voortgang-week-4.html
Johannes
Thanks Raymund,
Actually I am doing that by using UDF and Global Chang taking into consideration that the finish progress bar shuold be based on the the schedule %.But I was looking for an easier way.
Regards,
Ayman,
Baseline Progress Bar is not available in P6 in my opinion.
However if you want to show using the UDF, create UDF say Min (From or Start Date) and Ali (To or Finish Date).
On the bar option, create a Bar Name - BL Progress, Timescale - User Dates, then select the UDF for User Start Date and Use Finish Date. On the Bar Style - make the style & row the same as your baseline Bar.
Hope this will help.
Hi,
right click in the bar area, select the baseline bar and close. you will see it.
regrds,
kk
Raymund,
I could not see the attached picture ,however I'd like to show the blue bar on the baseline bar as we used to get it from P3,on other words, to show the planned progress on the baseline bar.
I am aware that it can be done by the user define fields,but it is lettle bit complicated,like to get an easy way.
Thanks for reply,regards,
Ayman,
Do you mean similar to this?
[[wysiwyg_imageupload:958:]]