Dear Friends

I want to know the Relation between Tender Program and Base Line program.

 

Regards

Arun.V

A
Arun Vasanth 👤 Member for 16 years 7 months

Thank you sir

Right now I am working in a Microtunneling project.In the Tender stage with limited information we submited  one Tender program with a sequence and duration,we got the work also.

Once the work awarded Client changed the sequence and duartion with  current situation with the joint meeting of We Maincontactor and the tunneling contractor.

Nw My Q.S  is saying that we have to submit a Base program with Tender sequence and Duration which is not going to happend.

 

What I have to do ???/Please help

A
Arun Vasanth 👤 Member for 16 years 7 months

Thank you Raymond

 

Is there any Mandatory rule that we have to follow the same duration and sequence 

of Tender program in the Base line program????

 

Regards

Arun Vasanth

R
Raymund de Laza 👤 Member for 16 years 6 months

Arun,

Tender Program = Preliminary Master Schedule attached with the Tender Docs. This part of the Tender Doc will present how you will plan to execute the Tender Project.
Baseline Program = Initial Schedule accepted or approved by client in the beginning of the implementation of Project. This detailed schedule will present how to execute the project on hand.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts