Good Evening Gents'
I'm trying to track my productivity through P6 along with quantity tracking. But while designing report i'm facing problem, how to call actual units per time , planned units per time & remaining units per time. Coz these three columns can help me in calculatin my planned, actual and forecast productivity. So if anybody have any idea about this please help me out.
Regards
Naeem
Hii Guys
I need Productivity Template and Progress Managment Template or format to make one for my ongoing project.
If possible please forward it to my e-mail my e-mail adress : [email protected]
Thanks
Aijaz Syed
Hi Mohammad,
In order to track productivity you need the following:
Plan Units per time - Budgeted Labour Units (Manhours or Mandays)
Earned Value - based on physical progress % complete (Budget Labour Units * % complete)
Actual Units per time - based on actual resources (manhours or mandays) this you need to input manually
Now, Productivity = Output (Earned) / Actual
Budgeted Labour Units - Progress Earned = Remaining Units per time
Budgeted at Completion (BAC) or Forecast at Completion = Remaining Units per time / Productivity
Cheers mate,
Daniel