MSP 2007 setting the reporting periods

Howdy... first post. dont shoot me if its a simple answer.

currently running the cashflow report in the visual report sections. our reporting period runs from the 20th to the 20th . how do i get the report to run 20-20 not 1-31?

so that our claim information matches our cost forecasts.

N
noura salma 👤 Member for 14 years 5 months

 

if you use Ms project 2007,

 

On the View menu, click Calendar-in the month, customize and you can change the duration

 

R
Richard Milsom 👤 Member for 14 years 5 months

i thought it was reasonably ckear, we run an accounting period that runs 20_20 of the month. how do i align the reporting function of the cshflow report in msp visual reports to tun 20_20 rather than 1_31?

i dont use the graph but typically use the pivot table infirmartion

forgive the spelling im not a spaz, just using a tablet with small buttons

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts