Budgeted units Vs Original duration

K
Kashif Khan 👤 Member for 14 years 6 months

whenever i fix budgeted units, the original duration remains the same... why?.. lets suppose if there is an activity of 10 days and the working units are 80 Manhours. Now if i appoint a resource and budget it only 40 hours. then original duration must be changed to 5 days and must not remain to 10 days. i am confused, plz help.

regards,

KK

K
Kashif Khan 👤 Member for 14 years 6 months

Thnaks daniel... sure it will work.. my office is off today.. tomorrow i will go and try and give u my feedback...

cheers.

kk

D
Daniel Limson 👤 Member for 24 years 7 months

Hi Kashif,

First off, that is the way it should be (the default), the duration should be fixed and the remaining units / time is normally the one that P6 calculates, it simply divide budgeted units / duration = Remaining Units / Time. Now if you want P6 to calculate the other way around you should define your duration type to 'Fixed Units/Time and then go to Edit, User Preferences and click calculations and in Resource Assingments you have two options click the bottom one where it says 'Recalculate Units, duration and Units/Time based on duration type'

Let me know if it works.

Regards,

Daniel

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts