Resources with no budget, but a cost to complete

K
Kevin Button 👤 Member for 22 years 11 months

Steven



At the project level, select the ’Calculations’ tab and untick the ’Link Budget and At Completion for not started activities’.



Doing this allowed me to have a remaining cost with a zero budget and also allowed a remaining duration to be different from original duration for non started activities.



Regards

S
Steven Oliver 👤 Member for 23 years 7 months

Unfortunately not. On a similar note, if you reduce the remaining duration of an activity that hasnt started, P3e automatically reduces the Original Duration. This isnt always the desired effect.

K
Kevin Button 👤 Member for 22 years 11 months

Steven



Something to try - in the resource assignment detail of the activity, insert a ’Cost Units Linked’ field and untick the box.



Regards

Forum Sponsor

Top Posters

sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts