Hi all could you please tell me whats Level1 to Level4 planning in projects????????????
Level1 to Level 4 schedule
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Hi Imran
Please find hereunder the link to my website and this part is related to the creation of levels using WBS structure.
I have the same for activtiy codes. Let me know is you are interested.
I note that the website is in the Dutch. Suggets to use Google translater. If not not clear let me know and i shall make the translation.
Trust this helps.
Johannes
http://plannenvoornietplanners.net/planning-lezen/kolommen/rijen-abc-en-d/indelen-met-wbs-codes.html
imran, tell us what you think with your question, and we'll give you some feedback.
You can get full info in the link below.
Essentilally Level one is a rolled up Master programme showing key activities, it goes to Level 5 which is an in depth deliverable program for construction purposes.
http://www.mosaicprojects.com.au/PDF/Schedule_Levels.pdf
Hi Kumar,
Thanks for your coordination.
Regards,
Imran
Dear
You can get the idea about levels of schedules from this site.
open the file of scedule levels
http://www.mosaicprojects.com.au/Planning.html#Roles
Regards,
1.....
1.1....
1.1.1.....
1.1.1.1.....