This free 45-page eBook is a collection of 19 essential rules, based on PMI and DoD standards and codes, which I find very important and useful. I tried to explain the reason behind each one and the way you can apply them in your schedules.
You can find more information and the download link here: http://en.khorramirad.info
TOC:
- Rule 01: Document the Scheduling Methodology
- Rule 02: The Schedule Should Have a Complete Scope
- Rule 03: Be Careful with Level-of-Effort Activities
- Rule 04: Activities Should Have Unique Names
- Rule 05: Activity Names should have a verb
- Rule 06: Each Activity Should Have at Least One Predecessor and One…
- Rule 07: Activities should not be Dangling
- Rule 08: Most Relationships should be FS
- Rule 09: Try not to Use SF Relationship
- Rule 10: You should not Use Large Lags
- Rule 11: Use Lags as Less as Possible
- Rule 12: Be Careful with Leads
- Rule 13: Be Careful with Negative Floats
- Rule 14: Activities should not Have Large Floats
- Rule 15: Do not Split Activities
- Rule 16: Do not Use a Lot of Date Constraints
- Rule 17: Make Milestones for Date Constraints
- Rule 18: Activities should not have Large Durations
- Rule 19: Use Only One Duration Unit
Hi Devaux,
I have seen your post here and I must say that it's perfectly right on what you have said.
Can you please explain me in detail,
Rule 20: Know the Value/Cost of Time on the Project, Is this Value of a Project?
Rule 22: Know the Doubled Resource Estimated Duration (DRED) or the Crash Duration of all CP activities and use them to optimize the schedule, How we will calculate this?
Thanks,
Samba
Dear Stephen;
Thanks for the comment. I would be happy to know that you’ve downloaded the ebook; donations are not as important as connecting to other professionals and having their feedback. It would also be great if you introduce it to your clients and students.
Thanks again
Yours
- Nader Khorrami Rad, PMP
Thank You Engr. Nader
One more: in general, I feel it's good practice to start the schedule with a single milestone or activity (source) and finish it similarly (sink). I'm not sure it rises to the level of a Rule: maybe a guideline?
Fraternally in project management,
Steve the Bajan
Hi,
This is a good starting list, thanks for sharing it.
Regards.
Hi, Nader. Good job, I think! I appreciate the effort, as last week I had been asked by a client to put together a similar checklist! I especially like Rules 04, 05, 10, and 19.
Without downloading the ebook (which I won't do because I don't think I should without making a donation), it's hard to know exactly what you mean by some of these (for example, 01, 02, 03, 12, 13, and 18.): what does "Be Careful with" mean, exactly?
I'd change Rule 06 to: "Each Activity's start Should Have at Least One Predecessor and Each Activity's Finish Should Have at Least One Successor." This would also obviate the need for Rule 07 (Dangling Activities).
I absolutely disagree with Rule 15 -- splitting of activities should never be done unthinkingly, but it can be VERY important to split activities that have an FF or SF predecessor, especially if they also have an SS or SF successor. Not doing this can lead to the Reverse Critical Path Anomaly, and delay the project for no reason other than the software's algorithm. Perhaps you could change Rule 15 to "Do not Split Activities Unthinkingly"?
I would add a couple more rules:
Rule 20: Know the Value/Cost of Time on the Project.
Rule 21: Strongly discourage doing out-of-sequence work. First, the schedule must be changed.
Rule 22: Know the Doubled Resource Estimated Duration (DRED) or the Crash Duration of all CP activities and use them to optimize the schedule.
Rule 23: Know the Critical Path Drag (if you don't know what this is, read this current Defense AT&L article) of all activities, their Drag Costs (see Rule 20) and their True Costs (True Cost = Resource Cost plus Drag Cost).
But overall, I feel you did a very nice job. If you like, I'd be happy to mention your ebook download site to clients and students. (But, like me, they probably won't donate anything!)
Fraternally in project management,
Steve the Bajan