Baseline Plan ?

Hello . I am facing a problem with baseline ...I have Maintained & assigned the baseline the Schedule ..but when I am sending this schedule by importing it to .xer file & sending it to my client via mail , When Client open  the schedule then there is no baseline maintained & assigned is showing....

Can any one tell me how to send the schedule with baseline ...

K
kumar s 👤 Member for 16 years 4 months

Dear,

sad thing is that there is no option to export the bseline schedule with the current schedule.
you have to Remove the baseline schedule from the current schedule and export both the schedules seperatly.Just name the schedules accordingly and tell the cleint to import both the schedules and then assign the bseline schedule to the current schedule

 

cheers

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts