what is the best way to allocate resources that are not involved in the execution of the works (not productive) as secretary, finance, accounting, quality manager, director, project manager ... etc..
Resources in primavera P6
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Make a dummy resours Call PM activity & assing this to all this type of activities
You could create one or several level of effort linked to start / end of your project or you can associated them to main activities.
Allocate associated ressources to each level of effort.
Frederic