HOW UNIT % COMPLETE IS UPDATED

How the unit % complete is getting updated?

Even though I apply the latest duration % for each activity, the unit % is getting considerably changed only when I change the Data Date. What Data Date has to do in the updation of the Unit & completion besides the duration percentages for the indivudual activities?

Could anyone please explain me why it is so?

Any feedback will be appreciable.

A
Anning Sofi 👤 Member for 14 years 4 months

 

Understand how % complete is treated in P6.

(Below is copy paste description from P6).



To indicate that the activity's percent complete will be entered by the user for this activity, select Physical. In this case, Activity % Complete = Physical % Complete.



To specify that the activity's percent complete be calculated from the original or planned and remaining durations, select Duration. In this case, Activity % Complete = Duration % Complete = (Original or Planned Duration – Remaining Duration) / Original or Planned Duration.



To specify that the activity's percent complete be calculated from the actual and remaining units, select Units. In this case, Activity % Complete = Units % Complete = (Actual Labor Units + Actual Nonlabor Units) / (Actual Labor Units + Actual Nonlabor Units +Remaining Labor Units + Remaining Nonlabor Units).

---

No correlation of Unit % complete to data date.

A
Anning Sofi 👤 Member for 14 years 4 months

Understand how % complete is treated in P6.

(Below is copy paste description from P6).



To indicate that the activity's percent complete will be entered by the user for this activity, select Physical. In this case, Activity % Complete = Physical % Complete.



To specify that the activity's percent complete be calculated from the original or planned and remaining durations, select Duration. In this case, Activity % Complete = Duration % Complete = (Original or Planned Duration – Remaining Duration) ¸ Original or Planned Duration.



To specify that the activity's percent complete be calculated from the actual and remaining units, select Units. In this case, Activity % Complete = Units % Complete = (Actual Labor Units + Actual Nonlabor Units) ¸ (Actual Labor Units + Actual Nonlabor Units +Remaining Labor Units + Remaining Nonlabor Units).

---

No correlation of Unit % complete to data date.

F
Frederic Fasquelle 👤 Member for 20 years 2 months

Hi Thomas,

Did you check your options. I mean Duration type & Percent Complete Type settings ?

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts