Activity renumbering will not work if the activity ID has and activity strucrure, and by itself mean something; for example
TP103300R0, activity structures is X-XX-XXX-XX-XX
for this example T=Terminal; P1=Podium 1, 033= CSI (concrete), 00 = sequential number R0 = Rev 0
If you can do export import, then it is fairly easy, and this process will not disturb the activity relationships:
1) Create a User Defined Field under the Enterprise, User Define Fields, attribute as Text, Let say you assign the User Define Field as NewID.
2) Create an export file (excel) with the fields, Activity ID, WBS, Activity Status and NewID. In excel, open you export, which should show the columns Activity ID, WBS, Activity Status and New ID, together with the data. Of course the New ID is still blank.
3) Under the NewID, indicate the new id corresponding to the original activity ID in your programme. You can of course use VLOOKUP in excel to make it easier.
4) Save this file.
5) Import this file to P6.
6) Using Global change, you can then set the criteria Activity ID = NewID in the global change parameters.
7) Run and commit the change. P6 will re ID your programme with the new acitivity IDs and still maintain the relationships between this new IDs similar to the relationships between the activities using the original IDs.
There is no easy way to change the Activity ID especially if you are using p6 V6.2, you can use renumbering ACTIVITY ID in the higher version of Primavera. But in P6 v6.2 and lower, you can use the global change. *go to tools, global change, new. and then, in the "if" parameter, Where - use WBS is under select the acitivities in the WBS you want to change. and in the "then" parameter select the activity = custom (write the activity codes you want) and then lick change, dnt commit changes, and exit the global change, I hope this can help you.
There is no easy way to change the Activity ID especially if you are using p6 V6.2, you can use renumbering ACTIVITY ID in the higher version of Primavera. But in P6 v6.2 and lower, you can use the global change. *go to tools, global change, new. and then, in the "if" parameter, Where - use WBS is under select the acitivities in the WBS you want to change. and in the "then" parameter select the activity = custom (write the activity codes you want) and then lick change, dnt commit changes, and exit the global change, I hope this can help you.
i tried to export and import the activities but the problem is when i import it,the activity relationship is gone.. can i use global change in changing my activity id's? thank you,
Ok, so the best way to do that is by Export to XLS spreadsheet and make the changes then Import to XRE. Pease, send me your E-Mail so I can send you the steps if you like.
Ok, so the best way to do that is by Export to XLS spreadsheet and make the changes then Import to XRE. Pease, send me your E-Mail so I can send you the steps if you like.
The best way to do that is from P6 go to Edit-Renumbering activities ID. I belive if you export and import to EXL you will lose the relations and some functions between the activities..
The best way to do that is from P6 go to Edit-Renumbering activities ID. I belive if you export and import to EXL you will lose the relations and some functions between the activities..
Thank you for answering my question,but i cannot find that option to renumber my activity id's,, for example All of my activities have an activity id's like this CAW9A.01, CAW9A.02 and so on, CAW9B.01, CAW9B.02 and so on, CAW9J.01, CAW9J.02 and so on,, I have 56 floor level to edit, in every floor level it is divided into 3 section named Section A, Section B, and Section J. In every section there are all have the same activities, my problem is how to change that particular activity id's in every floor in the fastest way.
In P6 ,go to Edit and select tab "renumber activities". Follow the instructions. I use this funtion frequently to create "intelligent" id coding.
Say, you have activities with the same discriptions but thes are in different WBS sections or on different fases of the work. Then it is advisable to renumber the activities to match the different fases to make sure that you can recognise the activities when you apply filters .
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Mark,
Activity renumbering will not work if the activity ID has and activity strucrure, and by itself mean something; for example
TP103300R0, activity structures is X-XX-XXX-XX-XX
for this example T=Terminal; P1=Podium 1, 033= CSI (concrete), 00 = sequential number R0 = Rev 0
If you can do export import, then it is fairly easy, and this process will not disturb the activity relationships:
1) Create a User Defined Field under the Enterprise, User Define Fields, attribute as Text, Let say you assign the User Define Field as NewID.
2) Create an export file (excel) with the fields, Activity ID, WBS, Activity Status and NewID. In excel, open you export, which should show the columns Activity ID, WBS, Activity Status and New ID, together with the data. Of course the New ID is still blank.
3) Under the NewID, indicate the new id corresponding to the original activity ID in your programme. You can of course use VLOOKUP in excel to make it easier.
4) Save this file.
5) Import this file to P6.
6) Using Global change, you can then set the criteria Activity ID = NewID in the global change parameters.
7) Run and commit the change. P6 will re ID your programme with the new acitivity IDs and still maintain the relationships between this new IDs similar to the relationships between the activities using the original IDs.
DONE.
Yes you are right Alfred...
yeah i know sir, but I think mark is asking how to use it in global change?
Hi Alfred,
I am using P6.1 and can change Activity ID's (Not renumbering only) of more than 75,000 Activities using the SDK function.
There is no easy way to change the Activity ID especially if you are using p6 V6.2, you can use renumbering ACTIVITY ID in the higher version of Primavera. But in P6 v6.2 and lower, you can use the global change. *go to tools, global change, new. and then, in the "if" parameter, Where - use WBS is under select the acitivities in the WBS you want to change. and in the "then" parameter select the activity = custom (write the activity codes you want) and then lick change, dnt commit changes, and exit the global change, I hope this can help you.
Alfred
There is no easy way to change the Activity ID especially if you are using p6 V6.2, you can use renumbering ACTIVITY ID in the higher version of Primavera. But in P6 v6.2 and lower, you can use the global change. *go to tools, global change, new. and then, in the "if" parameter, Where - use WBS is under select the acitivities in the WBS you want to change. and in the "then" parameter select the activity = custom (write the activity codes you want) and then lick change, dnt commit changes, and exit the global change, I hope this can help you.
Alfred
Mark,
Please let me know if it helps.....
Good Luck!
Hi,
This is my email [email protected] thank you
Hi Mr. Raymund,
How do i used SDK?is there a risk in my activities if i used that?i don't know how to use it..pls help me, thank you,
Hi Mark
if nothing works, you can use option REPLACE in edit,
Hi,
Use the Activity6x.xls via SDK.
hi hani,
i tried to export and import the activities but the problem is when i import it,the activity relationship is gone.. can i use global change in changing my activity id's? thank you,
Ok, so the best way to do that is by Export to XLS spreadsheet and make the changes then Import to XRE. Pease, send me your E-Mail so I can send you the steps if you like.
Ok, so the best way to do that is by Export to XLS spreadsheet and make the changes then Import to XRE. Pease, send me your E-Mail so I can send you the steps if you like.
Hi Mark
I am using P6 7
Regards Johannes
THE RE-NUMBERING ID OPTION IS NOT AVAILABLE ON P6.2
The best way to do that is from P6 go to Edit-Renumbering activities ID. I belive if you export and import to EXL you will lose the relations and some functions between the activities..
The best way to do that is from P6 go to Edit-Renumbering activities ID. I belive if you export and import to EXL you will lose the relations and some functions between the activities..
Hi,
Use the import / export from excel through SDK.
Hi Johannes,
Thank you for answering my question,but i cannot find that option to renumber my activity id's,, for example All of my activities have an activity id's like this CAW9A.01, CAW9A.02 and so on, CAW9B.01, CAW9B.02 and so on, CAW9J.01, CAW9J.02 and so on,, I have 56 floor level to edit, in every floor level it is divided into 3 section named Section A, Section B, and Section J. In every section there are all have the same activities, my problem is how to change that particular activity id's in every floor in the fastest way.
Thank you,
Hi Mark
In P6 ,go to Edit and select tab "renumber activities". Follow the instructions. I use this funtion frequently to create "intelligent" id coding.
Say, you have activities with the same discriptions but thes are in different WBS sections or on different fases of the work. Then it is advisable to renumber the activities to match the different fases to make sure that you can recognise the activities when you apply filters .
Johannes