Mid project baseline issues

 

Hi PP members,

I have just entered a project into P6 which is about half way completed. I need to create the baseline for the projects mid way position. To do this i created a new baseline based on the current project, but when I display the baseline bars some of them line up fine (should be equal to current bar) and some of them are miles off?

Why would it do this as I need the baseline to be equal to the current bars?

Can send a screenshot if it helps.

 

Thank You

Adam

J
James Buxey 👤 Member for 21 years 8 months

Adam

 

Glad I could help.

It is worth remembering the Planned Dates also determine where your Planned Value (BCWS) will profile to, which I have learnt to my cost over the 9 years working with Primavera!

 

Regards

James 

A
Adam Garnham 👤 Member for 14 years 8 months

Thank you James that fixed it!

I displayed the planned columns, exported to excel and copied the start/finish dates over the planned and imported it back into P6. Now the baseline bars match the current bars just like I needed.

Thank you for this!

J
James Buxey 👤 Member for 21 years 8 months

Hi

I am assuming you are baseling where you are now and so the baseline is to equal current?

 

Have you reviewed your 'planned dates' as if they do not match the start/finish dates at the time you baseline you will get a differance.

Add Planned Start and Planned Finish columns to your gantt chart and compare.

 

Regards

 

James

J
James Buxey 👤 Member for 21 years 8 months

Hi

I am assuming you are baseling where you are now and so the baseline is to equal current?

 

Have you reviewed your 'planned dates' as if they do not match the start/finish dates at the time you baseline you will get a differance.

Add Planned Start and Planned Finish columns to your gantt chart and compare.

 

Regards

 

James

R
Raymund de Laza 👤 Member for 16 years 6 months

I understand that you selected The Primary Baseline Under the Name Column but the corresponding Bar on the timescale column was shown as Plan Bar.[[wysiwyg_imageupload:888:]]

A
Adam Garnham 👤 Member for 14 years 8 months

Just checked and the bars selected are Primary Baseline and Baseline Milestones.

R
Raymund de Laza 👤 Member for 16 years 6 months

Adam,

On the Bars Window, make sure the timescale selected is Project Baseline Bar or Primary Baseline Bar  instead of Plan Bar.

 

Hope this will help.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts