P6_V.7.0 - ACTUAL LABOR UNIT/ACTUAL COST

Dear All,

Why actual Labor Units & Actual Cost change in the previus month when I Schedule Data Date to next moths?

Example :

Data Date = 31 December 11 ; Actual Labor Units = 100h ; Actual Cost = 100k

I Schedule the project with data date 31 Jannuary 2012 and input my progress with new value for Actual Labor units 150h and actual cost 150k

The problem is that the previus month with data date at 31 december 11 the actual labor units change in 90h and the actual costs are 80.. How I Can freeze all value of the previus months???

I can try to use Store perid performance editing all value but don't work

 

grazie

ciao

filippo

S
sadegh usman 👤 Member for 15 years 1 month

To ALL,

while waiting for the real solutions you can use userdefine add column to install your data,this will unchange your previous data.

 

 

F
filippo rando 👤 Member for 17 years 4 months

after assigned resourse to the activities,  you can input in budget cost columns the related cost as per resources/acttivity and it does work as hours budget . also you can work in activity table 'status' in labor unit box click right mouse and schoose labor cost.

if you have any solution for my problem write me please

 

ciao

filippo

O
orlando bryan 👤 Member for 19 years

I am trying to find a solution to very same problem, i would like to know how to prevent historical cost to remain unchanged. Is there a method of inputing period actual cost?

O
orlando bryan 👤 Member for 19 years

I am trying to find a solution to very same problem, i would like to know how to prevent historical cost to remain unchanged. Is there a method of inputing period actual cost?

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts