A couple of initial remarks: 1) A milestone can only be 0% complete or 100% complete. Nothing in between. Milestone is defined as its duration and work being zero, so saying a milestone is 60% complete would just give the result 60% times zero which is still zero.
2) Secondly, you can't have uncompleted activities/milestones in the past, however, many people still prefer to see the progress (zig-zag) line, so let's forget about that for a while.
To answer your question you could make a formula for a flag field asking that if "Baseline Finish" is less than "Status Date" and "Actual Finish" equals "NA" then the flag field would turn "Yes" or something similar. Then make a red bar style incorporating that flag field. All bars for uncompleted activities that should have been completed according to the baseline will now automatically turn red.
You right click on that specific activity, you click on information,you go to the advanced tab,then on the bottom left you click to make that activity a milestone,
In your case your program is not updated and scheduled on milestone date, you need to update the activities on which this milestone was dependent on and after that when you will reschdule the program then the milestone will become 100%.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Yvonne,
A couple of initial remarks: 1) A milestone can only be 0% complete or 100% complete. Nothing in between. Milestone is defined as its duration and work being zero, so saying a milestone is 60% complete would just give the result 60% times zero which is still zero.
2) Secondly, you can't have uncompleted activities/milestones in the past, however, many people still prefer to see the progress (zig-zag) line, so let's forget about that for a while.
To answer your question you could make a formula for a flag field asking that if "Baseline Finish" is less than "Status Date" and "Actual Finish" equals "NA" then the flag field would turn "Yes" or something similar. Then make a red bar style incorporating that flag field. All bars for uncompleted activities that should have been completed according to the baseline will now automatically turn red.
Regards,
Bo
You right click on that specific activity, you click on information,you go to the advanced tab,then on the bottom left you click to make that activity a milestone,
Hope you find it helful
Hlami
simple trick, right click on the milestone diamond and change its colour to red, though it is a manual trick but it will solve ur problem.
Thanks for the response but I want to be able to show the task is running late and have it highlighted in red.
Hi.
In your case your program is not updated and scheduled on milestone date, you need to update the activities on which this milestone was dependent on and after that when you will reschdule the program then the milestone will become 100%.
regards
kk