Friends,
I'm not able to configure MS-Project to work with only whole days. It's putting activities to begin in the middle of the day. I need activities or start one day earlier or later, not in the middle of a day.
Do anyone know how to configure that?
Thanks
José Otávio.
Jose, try checking the calendars. There could be a day that has non-standard (or nonconsistent) working hours per day (or totally different hour of start and finish hour per day).
cheers!
Keyel
Jose, try checking the calendars. There could be a day that has non-standard (or nonconsistent) working hours per day (or totally different hour of start and finish hour per day).
cheers!
Keyel
Hi Mike,
I found onething that was making a half day. When we put in the predecessor 80TI-50% we break a day. The correct way to do not break the activities this is writing 80TI-20 if you have an odd number of duration activity.
But now i have another strange situation. In the field "total margin of delay" (i don't know if it's the correct form because my programm version is portuguese) it shows 563,89 days, not 564.
There's no activity starting in a half day.
Thanks.
José Otávio
Hi Jose
Perhaps your fist activity finishes at the middle of the day and all the rest follow.
Best regards
Mike Testro