Has anyone done a study on installation rates for Cross Laminated Timber type of buildings
And how much faster it is compared to tradinal build
Dear James,
The typical activities are :
1) Substructure
a. Excavation
b. Foundation
c. Foundation Insulation and Insulation Protection
d. Fill
e. Slab on grade
2) Superstructure
a. Main Frames
b. Secondary Beams and Bracings
c. Cladding
d. Door and Windows
e. Gutters and Downspouts.
3) Electromechanical Works
4) Finishes
With kind regards,
Samer
Hi James
The usual sequence is.
1. Fix and Level sole plates
2. Install wall panels - line and level
3. Fix floor cassettes
Repeat 2 & 3 up to roof plate
4. Fix roof plate
5. Fix roof trusses.
Best regards
Mike Testro
Ive got some MSP examples for residential timber kit if thats any use?