Cost loaded Schedule

Hi everyone,

i am new to primavera 6, i want to load BOQ cost to the baseline schedule, i am loading cost as a resource for that i have created one resource COST, which is a non labor type, price/uint is 1, default units/time is 1/d  and max units/time is 1/d for this resource, So when i trying to load cost of any activity as Budgeted Cost the Budgeted Units are getting divided by 8. 

Budgeted Cost and Budgeted Units for an activity should be same.

Is this because we have 8 hours work/day in the Calendar assigned to the project  

Please help in this matter

Regards

Mudasir

M
mudasir dijoo 👤 Member for 15 years 4 months

Thanks Yaser and Raymund,

units formats n duration formats is already Day, Changed labor resource type to material resource type, now it is working

Budgeted unit is equal to Budgeted cost.

Regards

Mudasir

M
mudasir dijoo 👤 Member for 15 years 4 months

Thanks Yaser and Raymund,

units formats n duration formats is already Day, Changed labor resource type to material resource type, now it is working

Budgeted unit is equal to Budgeted cost.

Regards

Mudasir

Y
Yaser A. Al-Bustanji 👤 Member for 16 years

Dear Mudasir

You must convert the unit of time to "day"

to do that go to "edit" then choose "user prefernces" the choose "time units" the under "units formats" and "duration formats" choose "day"

 

Regards

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts