Hi all,
I have found a problem in my primavera program. I didnt assign any labour type resources to the activities of my program. But in Budget Labour units column, Primavera is showing some values?
Why it is coming like this?
Thanks in advance.......
question about labour units in P6
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Hi,
You might have copied your program from other programs that have labors assigned in the activities.
Yo need to reset labor units of all activities to zero.
Regards,