Please help me!!
Could anyone tell me step wise step procedure to update primavera schedule with actual dates on monthly basis
Please help me!!
Could anyone tell me step wise step procedure to update primavera schedule with actual dates on monthly basis
Actually I am updating my project on the basis of dates but for the activities which were sheuled to be start but not started as per data date how to update those activities so that our critical path won't change.?????
\
Actually I am updating my project on the basis of dates but for the activities which were sheuled to be start but not started as per data date how to update those activities so that our critical path won't change.?????
\
gaurav singh
What type of updation you are going to do?? Physical % or duration % or others?.Or you are asking about auto compute actuals?? is your program resource loaded?