The earliest possible date the remaining work for the activity can begin.
This date is calculated based on network logic, schedule constraints, and resource availability. Early start dates can change as the project progresses and as changes are made to the project management plan.
early finish:
The earliest possible date the activity can finish. Early finish dates can change as the project progresses and changes are made to the project management plan.
This date is calculated based on network logic, schedule constraints, and resource availability.
ef=es+duration
start(activities):
The current start date of the activity. For started activities, this is the actual start date. For not started activities, this is the planned start date until the project is scheduled. When scheduled, the start date field is set to the remaining early start date.
Resource Leveling always puts its resultant dates into the Planned Dates columns. It optionally also updates the CPM dates and the Start/Finish dates if you do not check the option, “Preserve scheduled early and late dates” in the Level Resources tab. It takes a genius to keep all of these operations and options straight (especially because most of the operations are not even documented in the manual.)
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
early start:
The earliest possible date the remaining work for the activity can begin.
This date is calculated based on network logic, schedule constraints, and resource availability. Early start dates can change as the project progresses and as changes are made to the project management plan.
early finish:
The earliest possible date the activity can finish. Early finish dates can change as the project progresses and changes are made to the project management plan.
This date is calculated based on network logic, schedule constraints, and resource availability.
ef=es+duration
start(activities):
The current start date of the activity. For started activities, this is the actual start date. For not started activities, this is the planned start date until the project is scheduled. When scheduled, the start date field is set to the remaining early start date.
source:
p6 data dictionary 8.1
Hi,
If Data Date = Project Start Date then Early Start = Start
If Activity already Started then Start = Actual Start and Early Start is the start date of remaining duration.
If activity not yet started then Start = Early Start.
Regards,
Andrew,
Resource Leveling always puts its resultant dates into the Planned Dates columns. It optionally also updates the CPM dates and the Start/Finish dates if you do not check the option, “Preserve scheduled early and late dates” in the Level Resources tab. It takes a genius to keep all of these operations and options straight (especially because most of the operations are not even documented in the manual.)
Hi,
Consider the following scenarios and see how the Start Date changes
1) Activity is not started -------- Start=Early Start
FInish = Early Finish
2)A ctivity has an actual start ----- Start=Actual Start
Finish = Early Finish
3) Activity is Complete - Start=Actual Start
Finish = Actual Finish
Regards
Amit
Check out my blog on Primavera at http://www.primaverablog.in
One addition, Ronald. Resources Leveling also affects start/finish dates.
Regards,
Andrew
Could you give me an example of that?
Regards,
Moutaz
Early Start dates are the result of the CPM calculation. Start dates are a combination of Early Start and Actual Start dates.