I have a programme, with reosurces assigned that have a cost assigned to them but they are not showing when imported by someone else when I export the Programme as an Xer file and e-mail accross to them, am I doing something silly here or is there a reason why the costs arent being exported even though the resources are showing up?
Budget Total Cost Not Exporting?