Dear All
Can any help in me in illustrating any practical Example of two activities having Start to Finish Relationship (SF) . I am confusing it with Finish to start (FS).
Regards
Planning Guy
Dear All
Can any help in me in illustrating any practical Example of two activities having Start to Finish Relationship (SF) . I am confusing it with Finish to start (FS).
Regards
Planning Guy
Simple example -
generator ON automatically ...as ur light gone -- Start to Finish ...
Thank you very much I got it
In the above example you cannot finish providing site security until new security is in place, if Site Security by Owner is delayed the finish of Site Security by Contractor shall be delayed.
It is rare relationships but it might happen.
Best regards,
Rafael