Export dates form P6 to Excel in European format

Hi,

I need to export the start and the finish dates from P6 to excel, but I need that when I have this in excel, I can use this information how dates no how text. And I want to know If somebody export to excel, the dates with date format no like text.

Thank you

M
mimoune djouallah 👤 Member for 19 years 7 months

in excel, select the columns, then data, text to columns, delimited, then date, select DMY, finish

excel will change the date format to your computer date format, then you can use the for your reports

T
Thomas Nicholson 👤 Member for 19 years 8 months

I suspect he's asking the question I asked last week.

When exporting from P6 the date appears in Excel as

'12-12-11' and using replace will not work as it claims it can't find the ' part you want to replace thus rendering it useless for analysis in Excel.

 

Thom  

T
Thomas Nicholson 👤 Member for 19 years 8 months

I suspect he's asking the question I asked last week.

When exporting from P6 the date appears in Excel as

'12-12-11' and using replace will not work as it claims it can't find the ' part you want to replace thus rendering it useless for analysis in Excel.

 

Thom 

R
Ronald Winter 👤 Member for 23 years 5 months

Alberto,

Are you asking how to format your dates as just a series of numbers?  You do this formatting in Excel.  Highlight the fields (or column) and then right-click, “format cells” and pick the desired way of displaying your dates.  Good luck!

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts