Planned Percent Complete

S
shima memar 👤 Member for 14 years 5 months

I'm using P6. I know that Primavera calculates Percents Complete like schedule%, unit%, physical% after starting the project and entering the actual values. but in the Planning Phase how can I get the planned % for each activity in every time period?

A
Akbar Ali 👤 Member for 15 years 10 months

Dears,

1. Please, explain how can I add a Column that can show the Planned Progress % based on the labor units. Schedule % complete doesn't roll up in summary, why ?

2. Can we introduce a user defined column that can incorporate calculations ? Like if we have Budgeted labour units = 5000 and we want to divide the individual activity's labor units by 5000, then we can have the planned progress activity wise. Please, guide.

J
jingjun zou 👤 Member for 18 years 2 months

Loading resources or cost in your Primavera schedule, and then you will get a s-curve in Primavera.

I think you can get your wanted in the S-curve.

S
shima memar 👤 Member for 14 years 5 months

Yes, I found out what I need is schedule%. but it doesnt show the rolled up schedule% for the whole project. how can I get it for the project?

K
kumar s 👤 Member for 16 years 4 months

Shima,

If you want to know the planned % complete then change the data date day/month wise as per your need.

do not schedule your project.

A
Ayman Eleish 👤 Member for 15 years 5 months

You can get the % shedule which presents the planned progress (time wise)

You can also assign cost loaded baseline and execute update progress(from tool tab)on the required data date to compare the cost wise percentages.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts