Hi
I am not able to shows dips in resource limits on public holidays , I have already assigned public holidays in project calendar
When i change the time line from week to month I have seen strange ups and down on my resource limit as show in picture 
Thanks in Advanced for your comments and support
Sorted assign Project Calendar to Resource Calendar :)