Durations

 hi, I'm an undergrad Mechanical Engineer and I'm having a bit of trouble setting up the durations for a project I'm working on. I have the project starting on 05/12/11 and the first task has duration set to 84 days, however the task is showing as complete by 01/02/12 (61 days latter). I've been trying to sort this out for about an hour and I'm starting to go nuts.

 There are 20 tasks in the project with varying durations, none of which are displaying in the project window as lasting as long as they should The whole project should last a little over 4 years and its ending a little after 1, despite having 2 tasks that take over 1000 days.

I'd really appreciate some help with this.

 

Craig

C
Craig McDougall 👤 Member for 14 years 6 months

 Hi Mike,

             sorry I took so long getting back her. You were right, everything pretty much went to plan afeter I got the calanders sorted out.

 

Craig

M
Mike Testro 👤 Member for 20 years 5 months

Hi Craig

Welcome to Planning Planet

With such a broad programme it is almost inevitable that the original estimated durations will have nothing to do with reality - so don't take them as correct.

Your problem is most likely calendar related.

Check that your duration column is formatted to working days if your calendar is set to working days.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts