WBS

X

M
Mike Testro 👤 Member for 20 years 6 months

Hi Jack

Do you mean a WBS or a delay impact programme?

At this stage you only need an outline programme at level 2 with broad bars.

Add the time required to deal with the gas main - I assume it is dead - and then a bit more for a complete survey of possible underground obstructions.

This will place the completion date beyond the target date - if it doesnt then for the purpose of this excercise make sure that it does.

Reduce the delay effect back to the target date by constructive acceleration by changing the work pattern from 8 hours a day to 9 hours.

Then add the christmas break in the calendar to generate another delay and report to your client that no further time reductions can be made so the target date will be at risk.

Good luck and best regards

Mike Testro

PS you can tell your teacher that Mike Testro says that a WBS is a side issue for bean counters and is not required in general planning operations.

Forum Sponsor

Top Posters

Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts