MSP 2007 Sub-Tasks Moving

Hi,

 

Can't see if this has been asked/answered before - if so, apologies.

A colleague has produced a detail schedule in MSP, and when saved it was fine with all sub-tasks showing under the correct summary task.

However, when it is reopened, all the sub-tasks appear to be distributed randomly around the schedule, additional blank lines appear, and other tasks are renumbered.

We have looked at saving with and without sorting on, there are no groupings set up, and we are only using the Gant Chart view.

Has anyone else come across this problem before, and if so, was there a solution.

 

Many thanks.

T
Tony McClennon 👤 Member for 23 years 8 months

Mike,

Thanks for confirming our suspicions. We managed to establish which copy was the latest "non-corrupted" version and fortunately this didn't require much work to replicate that in the corrupted file. Annoying though!!!

 

Thanks.

M
Mike Testro 👤 Member for 20 years 7 months

Hi Tony

You may have a virus or a corrupted file

Best regards

Mike Testro

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts