Cannot get Tertiary Baseline start & finish date columns to show up

Have a project where we had some issues and had to create a "Recovery" baseline.  We had set a project baseline at the beginning and had been showing the "BL Project" start and finish date columns and when I set the recovery (tertiary) baseline, went to "View", "Columns", chose BL1 start and finish colums but they just showed the original baseline dates.  So I chose BL2 start and finish and they did not show the recovery baseline dates.  Went so far as to restore the recovery baseline schedule, checked the dates and they were correct, so I went to "Project", "Maintain Baseline" and added it again as a baseline, went to "Project", "Assign Baselines", set it as the tertiary baseline again, tried to view the date columns and the same thing happened.  Have never had this happen before and I'm stumped.  

G
Gary Whitehead 👤 Member for 17 years 2 months

Try showing "BL3" dates instead of BL2

Project Baseline = BL Project

Primary = BL1

Secondary = BL2

Tertiary = BL3

 

Cheers,

 

G

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts