Primavera Contractor S Curves

T
TONY SEWELL 👤 Member for 15 years 9 months

Hi,

I want to be able to show a simple S curve based on a baseline and the remaining works. I only want this to be based on the duration of the works rather than resource.

 

Meaning that I can easily produce an S curve showing the profile of the works without having to resource the entire programme.

 

I am aware of the Resource Curve Tab, but these curves are not explained and can not be edited to include baseline etc.

 

All i can think at the moment is to create a new Report to export to excel to create my own, unless anyone is aware of another option?

 

Thanks

 

Tony

M
Mohammad Mojahid Akhtar 👤 Member for 18 years 4 months

Dear

You can get the S - Curve for duration. Do one thing put One Resourse (  say  - Parameter ) to all activity with 1/d .

then go to Report option and extract report from resourse & roll assignment.

you will get S -Curve.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts