Yea sorry I didnt mention what software I am using always forget to do so. (It is Primavera P6)
I took all constraints off my plan and then I added an Approval Period activity which is 2 weeks, then I put one constraint on my 1st activity of the plan to start on or after 1st April even though the 2 week approval period finishes on 17th March.
Thanks
Member for
16 years 7 months
Member for16 years7 months
Submitted by Gary Whitehead on Sun, 2011-11-06 18:52
Assuming you are using P6 (always best to mentino the software you are using when asking how to do something like this), you can mass-delete constraints by inserting the column "Primary Constraint", and using the "fill down" option.
Cheers,
G
Member for
24 years 9 months
Member for24 years9 months
Submitted by Patrick Weaver on Sat, 2011-11-05 10:52
I agree with Mike – make the approval an activity and it is in the schedule for monitoring and reporting. Lags simply create a space with no purpose; constraints are a total disaster as soon as anything changes for any reason. By highlighting the work of ‘approval’ you make it an important part of the overall progress of work.
My plan starts off with the Start milestone > first activity > 2 week Approval Period > next activity. The only thing is after the 2 weeks it only brings the date to the 19th March and the Activity after this doesnt start until 1st April.
On the Approval period activity is that just a task dependant type and the predeccessor is the 1st activity and successor is the next acitvity (1st April).
I have constraints from the MSP that I imported in from a client and these stayed within my plan as Start on or After. Shall I get rid of all constraints within my Plan as when I Data Date this all the dates change from the previous plan even though when you constraint them to start on a specific date so it stays fixed it still changes.
Member for
19 years 10 monthsHi Rhys A start on or after
Hi Rhys
A start on or after flag is OK for activity nr 1 in a programme.
It seem your approvals are already late - better start getting some notices in.
Best regards
Mike Testro
Member for
14 years 1 monthThanks for the help Guys Yea
Thanks for the help Guys
Yea sorry I didnt mention what software I am using always forget to do so. (It is Primavera P6)
I took all constraints off my plan and then I added an Approval Period activity which is 2 weeks, then I put one constraint on my 1st activity of the plan to start on or after 1st April even though the 2 week approval period finishes on 17th March.
Thanks
Member for
16 years 7 monthsRhys, Assuming you are
Rhys,
Assuming you are using P6 (always best to mentino the software you are using when asking how to do something like this), you can mass-delete constraints by inserting the column "Primary Constraint", and using the "fill down" option.
Cheers,
G
Member for
24 years 9 monthsI agree with Mike – make the
I agree with Mike – make the approval an activity and it is in the schedule for monitoring and reporting. Lags simply create a space with no purpose; constraints are a total disaster as soon as anything changes for any reason. By highlighting the work of ‘approval’ you make it an important part of the overall progress of work.
This is the approach adopted in the Guide to Good Practice in the Management of Time in Complex Projects, see: http://au.wiley.com/WileyCDA/WileyTitle/productCd-144433493X.html
Member for
14 years 1 monthHow do I get rid of all
How do I get rid of all constraints within my Project plan as I have over 500 activities and alot of them have constraints on.
I dont want to have to fish out each individual activity and change it to none.
Thanks
Member for
14 years 1 monthOk thanks for that Mike My
Ok thanks for that Mike
My plan starts off with the Start milestone > first activity > 2 week Approval Period > next activity. The only thing is after the 2 weeks it only brings the date to the 19th March and the Activity after this doesnt start until 1st April.
On the Approval period activity is that just a task dependant type and the predeccessor is the 1st activity and successor is the next acitvity (1st April).
I have constraints from the MSP that I imported in from a client and these stayed within my plan as Start on or After. Shall I get rid of all constraints within my Plan as when I Data Date this all the dates change from the previous plan even though when you constraint them to start on a specific date so it stays fixed it still changes.
Thanks
Member for
19 years 10 monthsHi Rhys The simplest way is
Hi Rhys
The simplest way is to add an activity of 2 weeks duration called Approval Period and link it FS tp predecessor and successor.
That way you can monitor progress on the approval.
My advice is Never - Ever add constraints to a programme - and I mean Not Ever.
Best regards
Mike Testro