" Planned Dates"

Please can soem one explaine to me what teh function of "Planned Dates" are in P6 and what benfit or use they are best used for ?

R
Ronald Winter 👤 Member for 23 years 5 months

Barry,

 

Planned Dates are your Baseline Dates.  When you display Baseline Schedule bars in the Gantt View, you are showing the other schedule’s Planned Dates.   Be careful what you do with these dates as they have the ability to automatically overwrite other date & duration columns.  Good luck!