I want to add quantity(area in sqm or no.s)

hi planners,

how can i assign and define the area of a project..means the schedule for glazing of a building,the wbs prepared is based on floors-

1st floor,2nd floor etc..

i want to add and show the total area of glass using in each floor and no of doors and windows in each floor..

 

1st Floor

Activity description      Percent complete          Original duration         Quantity

   Doors and windows                0                               9                                 -

       Glazing                              0                               14                               -

 

please reply..

vineeth
 

V
Vladimir Liberzon 👤 Member for 25 years 4 months

In Spider Project this field is called Activity Volume. Volume is a standard field and entering activity Volume and assigned resource productivities you don't need to enter activity duration - it is calculated by the software.

You may define material requirements per unit of volume, unit costs, resource assignment costs depending on volumes performed, etc.

In other softwares you shall use UDF as Mike proposed.

Photobucket

A
Anand Kurmi 👤 Member for 15 years

Hi Vineet,

What mike has written above holds true. Further if you can send me snapshot of the schedul of questioned area i shall be able to answer it

M
Mike Testro 👤 Member for 20 years 5 months

Hi Vineeth

You can set up user defined columns for this data or place the information on your resource modelling section.

Best  regards

Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts