hi planners,
how can i assign and define the area of a project..means the schedule for glazing of a building,the wbs prepared is based on floors-
1st floor,2nd floor etc..
i want to add and show the total area of glass using in each floor and no of doors and windows in each floor..
1st Floor
Activity description Percent complete Original duration Quantity
Doors and windows 0 9 -
Glazing 0 14 -
please reply..
vineeth
In Spider Project this field is called Activity Volume. Volume is a standard field and entering activity Volume and assigned resource productivities you don't need to enter activity duration - it is calculated by the software.
You may define material requirements per unit of volume, unit costs, resource assignment costs depending on volumes performed, etc.
In other softwares you shall use UDF as Mike proposed.
Hi Vineet,
What mike has written above holds true. Further if you can send me snapshot of the schedul of questioned area i shall be able to answer it
hi mike,
sorry to ask u again..if u dont mind please explain..
Hi Vineeth
You can set up user defined columns for this data or place the information on your resource modelling section.
Best regards
Mike Testro