Budgeted Labour Units

Good day all

can someone please explain why the budgeted labor units change when my plan is scheduled ?

I am using P6.2

thanking you

 

France

M
Mohammad Mojahid Akhtar 👤 Member for 18 years 4 months

Dear Mr.Amit

I am facing same problem

My " Duration Type " setting is

" Fixed Duration & Units/Time "

Can you explain Please .

I did not find answer in your Blog